for construction and structure course
September 17, 2006, after two years of construction, the main venue for the 2008 Beijing Olympic Games came to a final and most important part of the construction of its steel structure: the dismantling of the temporary support towers.
When presenting their stadium design to the Chinese jury, the Swiss architects Herzog & Meuron used the analogy of a bird’s nest. Everyone loved the idea of a bird’s nest and so they won. Perhaps because of the culinary association; in China, a bird’s nest is very expensive and believed to be extremely healthy, something you eat on very special occasions.78 Temporary supports were needed to support the birds nest roof during construction.
During construction, the crisscrossed interwoven steel roof construction of the bird’s nest roof was supported by 78 temporary steel columns. For additional stability, the huge ‘twigs’ were welded onto the supports. After completion of the bird’s nets construction the ‘twigs’ had to be cut off the support piers, before dismantling of the piers could start.In most western countries, cranes would have been hired to do the lifting job while welders would cut off the welds off the 78 supports laid during construction. However, due to the extreme high cost of hiring a number of 800-ton cranes for several days in China, a smarter and less expensive solution needed to be found. Key pre-requisites to the entire cutting-operation were safety, control, stability and cost. Enerpac, known from many complex hydraulic applications around the globe and in the Chinese market especially for their hydraulic solutions for moving roofs (NanTong stadium) and moving structures (Shanghai concert hall) was consulted.
Cutting the ‘twigs’ from the temporary supports.
Basically the disconnecting and dismantling process of the temporary supports comes down to synchronically and fully controlled lifting the structure of its supports, cutting the welds, followed by controlled and synchronized stage-lowering to allow the removal of the 50mm think leveling plates that were used during construction. Computer-controlled hydraulics is the perfect match for jobs like this, and Enerpac was granted the contract to perform the stage lifting and lowering of the roof. The entire configuration including the central computer, satellite computer-controllers, 156 double-acting high-pressure hydraulic cylinders and 55 electronically controlled hydraulic power units was specified and custom designed by ENERPAC. For added safety, control and accuracy, multi-functional valves, load sensors, stroke sensors, shift detection and a digital feedback system were integrated.
Enerpac hydraulic systems on each of the 30 piers of the inner ring.
After successful disconnecting the 45.000 ton steel structure from its temporary support piers, last year November, the bird’s nest stood on its own “feet” for the first time.